COMPLETED PROJECT’S LIST

S.NO

PROJECT NAME

DURATION

PERIOD

1

Construction of Well location Mehar-3 & Rehabilitation works of Mehar-1 and Mehar-2

90 Days Oct-2011 To Dec-2011
2

Construction of well location, Rig Camp & Access Road Sofiya-2 Mehar.

60 Days Dec-2012 To Feb-2012
3

Construction of well location, Rig Camp site & Access Road Rehan-2 (Mubarak Block).

35 Days 20 Feb-2013 To March-2013
4

Construction of well location, Rig Camp site & Access Road Rehmat-4 (Mubarak Block).

45 Days April-2013 To 15 May-2013
5

Construction of well location Putra-1

45 Days 2008
6

Evaporation Pond at RGP.

30 Days 2008
7

Construction of OMV Residence Camp at Mehar Block.

30 Days 2012
8

Construction of Box Culverts at Mehar Block.

45 Days 2013
9

Water Supply Scheme for Community at Mehar.

30 Days 2013
10

Construction of Water well bore at RGP (Mubarak Block).

25 Days 2013
11

Civil Works at Camp RGP (Mubarak Block).

35 Days 2013
12

Construction of well location, Rig Camp site & Access Road Jaskani-1

45 Days 2014
13

Construction of well location, Rig Camp site & Access Road Miano-18

35 Days 2014
14

Balance Civil Work of Mehar Gas Field

150 Days 2014/2015
15

Construction of Bridge on Mazarani River

90  Days 2015
16

Construction of well location, Rig Camp site & Access Road Kohar-1

35 Days 2015
17

Miano-18 Wellhead Development Project

42 days 2015
18

Miano 18 to Miano 15 Flowline (1.5 KM)

30 days 2015
19

Miano 15 to Miano 11 Flowline (Loopline) 5.5 KM

50 days 2015