Rig Camp site & Access Road Sofia-2

Sofia-2-(1)

Project: Construction of well location, Rig Camp site & Access Road Sofia-2

Client: OMV Maurice Energy Ltd.

Location: Mehar (Sindh) Distt: Dadu

Period: 60 Days (Year 2012)

Scope:

  • Construction of Access Road, Rig Camp location culverts etc.
  • Cutting and Filling of well site
  • Construction Celler Pad, Rig Pad, cutting pit, waste pit,
  • Construction of Flare Pit, Mud Pit,
  • Installation of Fence around the well side.
  • Construction of Parking Area and Fuel Tank area

Rig Camp site & Access Road Mehar-3

Mehar-3-(1)

Project: Construction of well location, Rig Camp site & Access Road Mehar-3

Client: OMV Maurice Energy Ltd.

Location: Mehar (Sindh) Distt: Dadu

Period: 90 Days (Year 2011)

Scope:

  • Construction of Access Road, Rig Camp location culverts etc.
  • Cutting and Filling of well site
  • Construction Celler Pad, Rig Pad, cutting pit, waste pit,
  • Construction of Flare Pit, Mud Pit,
  • Installation of Fence around the well side.
  • Construction of Parking Area and Fuel Tank area

Rig Camp site & Access Road Jaskani-1

Jaskani -1

Project: Construction of well location, Rig Camp site & Access Road Jaskani-1

Client: OMV (PAKISTAN).

Location: Khanpur Mahar (Sindh) Distt: Ghotki

Period: 45 Days (Year 2014)

Scope:

  • Construction of Access Road, Rig Camp location culverts etc.
  • Cutting and Filling of well site
  • Construction Celler Pad, Rig Pad, cutting pit, waste pit,
  • Construction of Flare Pit, Mud Pit,
  • Installation of Fence around the well side.
  • Construction of Parking Area and Fuel Tank area

Rig Camp site & Access Road Miano 18

Miano-18-Location-(1)

Project: Construction of well location, Rig Camp site & Access Road Miano 18

Client: OMV (PAKISTAN).

Location: Khanpur Mahar (Sindh) Distt: Ghotki

Period: 35 Days (Year 2015)

Scope:

  • Construction of Access Road, Rig Camp location culverts etc.
  • Cutting and Filling of well site
  • Construction Celler Pad, Rig Pad, cutting pit, waste pit,
  • Construction of Flare Pit, Mud Pit,
  • Installation of Fence around the well side.

Rig Camp Site & Access Road Kohar-1

Kohar-1-(1)

 

 

Project: Construction of well location, Rig Camp site & Access Road Kohar-1

Client: OMV Maurice Energy Ltd.

Location: Mehar (Sindh) Distt: Dadu

Period: 35 Days (Year 2015)

Scope:

  • Construction of Access Road, Rig Camp location culverts etc.
  • Cutting and Filling of well site
  • Construction Celler Pad, Rig Pad, cutting pit, waste pit,
  • Construction of Flare Pit, Mud Pit,
  • Installation of Fence around the well side.
  • Construction of Parking Area and Fuel Tank area

Construction of Bridge on Mazarani River

Bridge (3)

Project: Construction of Bridge on Mazarani River

Client: OMV Maurice Energy Ltd.

Location: Mehar (Sindh) Distt: Dadu

Period: 90 Days (Year 2014)

Scope:

  • Pile, Footings, Piers works for Bridge
  • Construction of Installation of Pre-stress Girder
  • Stone Pitching, Ancillary works etc.

Balance Civil Works of Mehar Gas Field

BCW-(1)

Project: Balance Civil Works of Mehar Gas Field

Client: OMV Maurice Energy Ltd.

Location: Mehar (Sindh) Distt: Dadu

Period: 150 days (Year 2014)

Scope:

  • Construction Laundry Building, Junior Accommodation, Senior Accommodation, Masjid, Parking Shed, Workshop Building,
  • Watch towers etc.
  • Water Supply Network, Sewerage Network
  • Internal Roads, Foothpath etc.
  • Electrical, Telecommunication, data Network installation
  • External Lighting system and Installation of DBs.